General Operations Team: Difference between revisions
From Pumping Station One
Garynhouse (talk | contribs) |
Garynhouse (talk | contribs) |
||
| Line 102: | Line 102: | ||
5. Relocated booth air drop to left side of booth. | 5. Relocated booth air drop to left side of booth. | ||
6. Document electrical. Document panel door legends to wiki(DONE GN). Update CAD with current wiring (mostly done AM). Plot locations of projected wiring for HM/ | 6. Document electrical. Document panel door legends to wiki(DONE GN). Update CAD with current wiring (mostly done AM). Plot locations of projected wiring for HM/CM/General move (needs mostly done SB and Hosts, CAD in process AM, bid spec GN, AM & BD tbd). | ||
7. Transition member paid storage to share with MMT (done GN & Scott Yoder ) | 7. Transition member paid storage to share with MMT (done GN & Scott Yoder ) | ||