== Background ==
== Background ==
We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link).  This vote will allocate the money to build-out the 3515 and modify the existing space as indicated below.
We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link).  This Build-Out vote describes how the initial build-out of the combined spaces will occur.  We allocated $5000 for buildout expenses through the 2016 budget vote.


This Build-out vote describes  The 2016 budget vote allocated $5000 for build-out expenses. 
* HVAC
* HVAC
** Install AC in new lounge.  
** Install AC in new lounge. $300
** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser.  The roof perforation will be done by a professional roofer.  Interior ducting can be done by volunteers.  Makeup air? Materials: ducting, elbows, hangers.
** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser.  The roof perforation will be done by a professional roofer.  Interior ducting can be done by volunteers.  Makeup air? Materials: ducting, elbows, hangers. $300
** Install ventilation duct and fan for the kitchen.  Use the duct currently used by the laser.
** Install ventilation duct and fan for the kitchen.  Use the duct currently used by the laser. $300
** Install ventilation duct and fan for small metals (jewelry).   
** Install ventilation duct and fan for small metals (jewelry).  $300
** Move dust collection system for woodworking.  Materials: ducting, elbows, wyes, hangers blast gates. Purchase new filter for the Jet collector to aid with the transition to the new system.
** Move dust collection system for woodworking.  Materials: ducting, elbows, wyes, hangers blast gates. Purchase new filter for the Jet collector to aid with the transition to the new system. $900
** Extend ventilation duct  and add hood for hot metals.
** Extend ventilation duct  and add hood for hot metals. ??


* Electrical
* Electrical
** Install new power outlets for cold metals and hot metals.  Materials: conduit, wire, outlets.
** Install new power outlets for woodworking, cold metals and hot metals.  Materials: conduit, wire, outlets. $1500
** Install 2 240v power outlets for woodworking.


* Plumbing
* Plumbing
** Install work sink on the wall adjacent to the kitchen, next to the sliding fire door.  Materials: sink, misc. plumbing.
** Install work sink on the wall adjacent to the kitchen, next to the sliding fire door.  Materials: sink, misc. plumbing. $300
** Install work sink at the top of the stairs next to upstairs bathroom.
** Install work sink at the top of the stairs next to upstairs bathroom. $300
** Remove old sink in new lounge.
** Remove old sink in new lounge.
*Install a partition between the Elston and alley sides of the new space.


*Obtain necessary permits if they are deemed appropriate.
*Obtain necessary permits if they are deemed appropriate.
Line 37: Line 36:
*Move equipment to new locations.
*Move equipment to new locations.


* Clean dust from trusses, walls, etc. in old shop. {we may want to hire this out}
* Clean dust from trusses, walls, etc. in 3519 shop.  
 
*Remove tool cage walls.
*Remove tool cage walls.


*Purchase and install shelving for member storage.
*Purchase and install shelving for member storage. $1000
   
   
*Benches for general work area.
*Benches for general work area.
Line 47: Line 45:
* Compressed air for new shop. {Run tubing from old shop? Or get additional compressor? Also need air for laser/ CNC?}
* Compressed air for new shop. {Run tubing from old shop? Or get additional compressor? Also need air for laser/ CNC?}


 
* Rent or purchase a section of rolling scaffolding.  This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning.
 
 
Expense spreadsheet:
insert link here
 
 


This vote assumes that these tasks will be performed  by the landlord before we move in:
This vote assumes that these tasks will be performed  by the landlord before we move in:
Line 60: Line 52:
*Fix roof leaks.
*Fix roof leaks.
*Upgrade the lighting.
*Upgrade the lighting.
*Repair the air conditioning system.


== Language ==