Tool Cage Proposal: Difference between revisions
From Pumping Station One
No edit summary |
No edit summary |
||
| Line 1: | Line 1: | ||
== Sponsor == | == Sponsor == | ||
| Line 25: | Line 26: | ||
The initial estimate cost for the materials is $750 for 520' of steel tubing and $300 for twelve sheets of 8' by 4' half inch plywood. | The initial estimate cost for the materials is $750 for 520' of steel tubing and $300 for twelve sheets of 8' by 4' half inch plywood. | ||
== Schedule == | |||
The cage will be built in the first week of March. Once the vote is approved the steel will be purchased, and all pieces will be cut to length and organized so that the actual welding and assembly of the cage can be finished within one weekend. | |||