== Background ==
== Background ==
We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link).  This Build-Out vote describes how the initial build-out  of the combined spaces will occur.  We allocated $5000 for buildout expenses through the 2016 budget vote.   
We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link).   


This Build-out vote describes  The 2016 budget vote allocated $5000 for build-out expenses.   
This Build-Out vote describes the initial build-out of the combined space. The type of wall or partition required to separate woodworking and hot metals has not been determined, so an estimate for that is not included. A vote for additional money for the wall may be necessary. 
* HVAC
 
The 2016 budget vote allocated $5000 for build-out. The expenses for the activities listed below should fall within that budget.  If there are unforeseen expenses another vote may be necessary.
   
* HVAC
** Install AC in new lounge. $300
** Install AC in new lounge. $300
** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser.  The roof perforation will be done by a professional roofer.  Interior ducting can be done by volunteers.  Makeup air? Materials: ducting, elbows, hangers. $300
** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser.  The roof perforation will be done by a professional roofer.  Interior ducting can be done by volunteers.  Makeup air? Materials: ducting, elbows, hangers. $300
Line 29: Line 32:
** Install work sink at the top of the stairs next to upstairs bathroom. $300
** Install work sink at the top of the stairs next to upstairs bathroom. $300
** Remove old sink in new lounge.
** Remove old sink in new lounge.
 
** Compressed air for the
*Obtain necessary permits if they are deemed appropriate.
*Obtain necessary permits if they are deemed appropriate.
*Remove temporary partition in new lounge. Paint and repair drywall if necessary.  Materials: paint.
*Remove temporary partition in new lounge. Paint and repair drywall if necessary.  Materials: paint.
*Move equipment to new locations.
*Move equipment to new locations.
 
* Vacuum dust from trusses, walls, etc. in 3519 shop.  
* Clean dust from trusses, walls, etc. in 3519 shop.  
*Remove tool cage walls.
*Remove tool cage walls.
 
*Purchase and install shelving for member storage. $500
*Purchase and install shelving for member storage. $1000
*Benches for general work area.
*Benches for general work area.
 
* Run compressed air for the laser and hot metals. $300
* Compressed air for new shop. {Run tubing from old shop? Or get additional compressor? Also need air for laser/ CNC?}
* Rent or purchase a section of rolling scaffolding.  This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. $300
 
* Rent or purchase a section of rolling scaffolding.  This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning.  


This vote assumes that these tasks will be performed  by the landlord before we move in: