Electrical: Difference between revisions

From Pumping Station One
Mskilton (talk | contribs)
No edit summary
Mskilton (talk | contribs)
Boiler room circuits. PP1-1 scares me
Line 8: Line 8:


Back of the shop by the loading dock. Can't miss it.
Back of the shop by the loading dock. Can't miss it.
Lots of sketchy shit in this one.
Single phase and 2 pole circuits wired to 3 phase breakers. One apparent circuit wired to 2 panels.
Several high amp 3 phase breakers that are unmapped.
{|Class="wikitable sortable" border="1" style="td { border: 1px solid #000000}"
|-
! Breaker # !! Used !! What Is It
|-
| 14&16&18 || unused || 3 phase, 20 amp, 3 black. Wiring trough, boiler room. Possible dust collection circuit thru existing disconnect.
|-
| 19&16&18 || used || 2-120v circuits on a 3 phase breaker. Blue wires. Boiler & zone pumps, this is bad and wrong.
|-
| 22 || unused || this is a stray 208v single red wire on a 3 phase breaker that runs to a 3 phase disconnect in the boiler room. Should be disconnected and abandoned.(used to be paired with wires pp1-2 # 35&37)
|-
|}


'''PP1-2'''
'''PP1-2'''
Line 27: Line 47:
|26 || yes, works || Currently connected to the entire east wall. This includes dust collector and Clausing electronics. Please do not connect chop saw table to east wall while others are working.
|26 || yes, works || Currently connected to the entire east wall. This includes dust collector and Clausing electronics. Please do not connect chop saw table to east wall while others are working.
|-
|-
| 35&37 || used || 40 amp 1 phase 240v thru a 3 phase disconect used as junction box to another 3 phase disconnect used as a 1 phase 35 amp disconnect. Compressor.
|}
|}